Project "Sačurov"

Company Chemkostav a.s., Michalovce started on December 17th, 2012 with the project "Construction work on biogas stations Sačurov".
Beneficiary of the Work is firm VODNÉ A ENERGETICKÉ STAVBY (WATER AND ENERGY BUILDINGS), spol. s.r.o.

On the basis of the contract of work there will be performed work on objects of water supply, sewerage, manipulation surface and homogenization. There also will be implemented the foundation of the dosing tank, of the fermenter, of the storage tank, of the gas engine room, of the cogeneration, of the residual gas burner, of the substation, of the sanitary container, mast lightning, of the fire tanks, of the switch room and of the control center. Expected date of completion of the building is set on April 30th, 2013.