South City - primary infrastructure - water supply systems

Beneficiary:Delta Construction, s.r.o.
Supplier:Chemkostav, a.s.
Construction duration:May, 2013 - May, 2014

Basic information

All activities will be implemented to prepare the necessary infrastructure for the new territory, where the future construction is planned. Therefore, the complex modifications will be implemented.

In terms of drinking water, the expansion and extension of the existing water supply will be carried out and also the new lines will be created. The total length of the pipeline under the design is approximately 3 020 meters. Section under the four-lane Panonska road will be implemented by extruding of pipes under the road, with a diameter of 1 meter and a length of 64 meters.

Part of the works is the sewage disposal of area around South City. This will be ensured by pressure and gravity drainage
. This will create a new sewage network of around 1 610 meters.