SKK Ružomberok and WWTP Liptovská Teplá, Liptovské Sliače

Beneficiary:Vodárenská spoločnosť Ružomberok, a.s.
Supplier:Chemkostav, a.s.
Construction duration:January, 2014 - July, 2015

Basic information

The project addresses the agglomeration Ružomberok, Sliače and Lúčky in which all activities will be implemented. The main objective of the project is to ensure the collection and treatment of urban waste water in the region of Dolný Liptov and achieve at least 99.2% of the connection of inhabitants to public sewers. The project will help to the newly connection to the sewer to 5,730 inhabitants.
 
The project involves the construction of sewerage network in Ružomberok (urban district Biely Potok, Černová and Hrboltová) and in the villages  Liptovské Sliače, Liptovská Teplá, Ivachnová and Likavka in a total length of 40 116 m, including the implementation of 1698 sewer connections. Furthermore, the project addresses the expansion and reconstruction of WWTP Liptovská Teplá.