Construction work on biogas stations Sačurov

Beneficiary:Vodné a energetické stavby (WATER AND ENERGY BUILDINGS), spol. s r.o.
Supplier:Chemkostav, a.s.
Construction duration:December, 2012 - October, 2013

Basic information

Project is located in the village Sačurov. On the basis of the contract of work there will be performed work on objects of water supply, sewerage, manipulation surface and homogenization. There also will be implemented the foundation of the dosing tank, the fermenter, the storage tank, the gas engine room, the cogeneration, the residual gas burner, the substation, the sanitary container, mast lightning, the fire tanks, the switch room and the control center.