Biogas plant Zemplínska Teplica

Beneficiary:Alkon, Košice a.s.
Supplier:Chemkostav, a.s.
Construction duration:November, 2011 - August, 2012

Basic information

Biogas plant converts organic biomass (according to the recipe) to methane and carbon dioxide by microorganisms of the available energy resources in the locality.

The construction comprised of 4 building objects. The cogeneration building included a brick object based on reinforced concrete foundation strips. The ceiling is consisted of TT ceiling panels, on which the insulation and roof insulation coating is implemented. This facility will serve as the operational and technological building. Stock of gas is implemented from the steel structures and cladding corrugated sheets. The building will serve as a space for the bag of gas accumulation. Primary and secondary fermenters including the service basements within this building the monolithic service basements No.1, 2, 3 were carried out. They are used for technological distributions and facilities. Also there were also monolithic circular tank thus fermenters built, with the trapezoidal metal sheet cladding and roofing with waterproofing and insulation coating. Within the all work, the fence around the object has been carried out.

Construction of a biogas plant including the related infrastructure, located in the cadastral area of Zemplínska Teplica, Trebišov County, was successfully completed and handed over to Beneficiary in August 28th, 2012.